Energy isolation verification checklist

Use alongside your site’s written energy control procedure for this equipment. Every energy source must be listed and verified.

Equipment / tag no.
Date / time
Procedure reference
Authorised person

Preparation and isolation

  • All energy sources for this equipment are identified (electrical, mechanical, hydraulic, pneumatic, chemical, thermal, gravity)
  • Affected people have been told the equipment will be shut down
  • Equipment is shut down using the normal stopping procedure
  • Each energy source is isolated at its energy-isolating device (not a control circuit)
  • Each person exposed has applied a personal lock / tag

Stored energy and verification

  • Stored energy is released, restrained or blocked (springs, accumulators, capacitors, raised parts, trapped pressure, heat)
  • Isolation is verified by attempting to start / operate from normal controls
  • Absence of voltage / pressure is proven with suitable, checked test equipment where relevant
  • Controls are returned to OFF / neutral after the verification attempt

Energy sources and isolation points

Energy typeIsolation pointLocked byVerified how

Confirmation

Verified by (signature)
Witness (where required)

General discussion aid, not a risk assessment, permit or procedure. Adapt to your site’s hazards, legal requirements and competent advice.